MB6-884 · Question #68

You are configuring a Lean production flow in Microsoft Dynamics AX 2012. Which cost group type should you assign to a subcontracting work cell?

The correct answer is A. indirect. See the full explanation below for the reasoning.

Question

You are configuring a Lean production flow in Microsoft Dynamics AX 2012. Which cost group type should you assign to a subcontracting work cell?

Options

  • Aindirect
  • Bdirect outsourcing
  • Cexternal operation
  • Ddirect materials

How the community answered

(53 responses)
  • A
    77% (41)
  • B
    6% (3)
  • C
    2% (1)
  • D
    15% (8)