In Microsoft Dynamics AX 2012, the Capable to Promise (CTP) explosion is run for an item on a sales order line. The system determines that a date requested on the sales order line cannot be met…
The correct answer is A. confirmed ship date. See the full explanation below for the reasoning.
Question
In Microsoft Dynamics AX 2012, the Capable to Promise (CTP) explosion is run for an item on a sales order line. The system determines that a date requested on the sales order line cannot be met. Which field is updated to reflect the date calculated by the CTP functionality?
Options
- Aconfirmed ship date
- BConfirmed delivery date
- CRequested ship date
- DScheduled period date
How the community answered
(44 responses)- A75% (33)
- B2% (1)
- C7% (3)
- D16% (7)
Community Discussion