When creating a single transfer activity in Microsoft Dynamics AX 2012, which setting will generate an error when validating the production flow version?

The correct answer is D. Setting the product type to Semi-finished product. See the full explanation below for the reasoning.

Question

When creating a single transfer activity in Microsoft Dynamics AX 2012, which setting will generate an error when validating the production flow version?

Options

  • ASelecting the Update on hand on receipt check box.
  • BSelecting the Update on hand on pick check box.
  • CSetting the product type to Finished product,
  • DSetting the product type to Semi-finished product.

How the community answered

(46 responses)
  • A
    7% (3)
  • B
    2% (1)
  • C
    13% (6)
  • D
    78% (36)