Which order type is used by Master Planning to create planned orders for items supplied by Kanbans?
The correct answer is B. purchase order. See the full explanation below for the reasoning.
Question
Which order type is used by Master Planning to create planned orders for items supplied by Kanbans?
Options
- AKanban
- Bpurchase order
- Ctransfer
- Dproduction
How the community answered
(60 responses)- A5% (3)
- B73% (44)
- C7% (4)
- D15% (9)