Microsoft
MB6-884 · Question #54
In Microsoft Dynamics AX 2012, you configure a Kanban rule with the following values: . Default quantity is blank (not set). - Minimum quantity is 50 pieces. - Maximum quantity is 100 pieces…
The correct answer is B. 4 orders with 100 pieces and 1 order with 40 pieces. See the full explanation below for the reasoning.
Question
In Microsoft Dynamics AX 2012, you configure a Kanban rule with the following values: . Default quantity is blank (not set).
- Minimum quantity is 50 pieces.
- Maximum quantity is 100 pieces.
- Alert boundary minimum is 10 pieces.
You run the Master scheduling for an item that has the coverage group set up with the Min/Max coverage code. The item has an issue quantity of 440 pieces. As a result of the Master Scheduling, multiple planned orders of type Kanban are created. What are the required quantities in the planned orders that are created?
Options
- A9 orders with 50 pieces
- B4 orders with 100 pieces and 1 order with 40 pieces
- C5 orders with 100 pieces
- D4 orders with 100 pieces and 1 order with 50 pieces
How the community answered
(20 responses)- A5% (1)
- B70% (14)
- C15% (3)
- D10% (2)
Community Discussion