In Microsoft Dynamics AX 2012, you configure a Kanban rule with the following values: . Default quantity is blank (not set). - Minimum quantity is 50 pieces. - Maximum quantity is 100 pieces…

The correct answer is B. 4 orders with 100 pieces and 1 order with 40 pieces. See the full explanation below for the reasoning.

Question

In Microsoft Dynamics AX 2012, you configure a Kanban rule with the following values: . Default quantity is blank (not set).

  • Minimum quantity is 50 pieces.
  • Maximum quantity is 100 pieces.
  • Alert boundary minimum is 10 pieces.

You run the Master scheduling for an item that has the coverage group set up with the Min/Max coverage code. The item has an issue quantity of 440 pieces. As a result of the Master Scheduling, multiple planned orders of type Kanban are created. What are the required quantities in the planned orders that are created?

Options

  • A9 orders with 50 pieces
  • B4 orders with 100 pieces and 1 order with 40 pieces
  • C5 orders with 100 pieces
  • D4 orders with 100 pieces and 1 order with 50 pieces

How the community answered

(20 responses)
  • A
    5% (1)
  • B
    70% (14)
  • C
    15% (3)
  • D
    10% (2)

Community Discussion

No community discussion yet for this question.

Full MB6-884 Practice