Microsoft
MB6-884 · Question #28
When creating a new planned Kanban order from the supply schedule screen, which value is required?
The correct answer is A. BOM number. See the full explanation below for the reasoning.
Question
When creating a new planned Kanban order from the supply schedule screen, which value is required?
Options
- ABOM number
- BItem number
- CRoute number
- DVendor
How the community answered
(31 responses)- A81% (25)
- B10% (3)
- C6% (2)
- D3% (1)
Community Discussion