You need to assign service terms to a production flow activity in Microsoft Dynamics AX 2012. What must you do first?
The correct answer is B. Attach a resource group containing at least one vendor resource to the production flow. See the full explanation below for the reasoning.
Question
You need to assign service terms to a production flow activity in Microsoft Dynamics AX 2012. What must you do first?
Options
- AAttach at least one vendor resource to the production flow.
- BAttach a resource group containing at least one vendor resource to the production flow.
- CAttach at least one vendor resource to the production flow activity.
- DAttach a resource group containing at least one vendor resource to the production flow activity.
How the community answered
(42 responses)- A14% (6)
- B74% (31)
- C5% (2)
- D7% (3)