You plan to report a bill of materials (BOM) as finished. You need to ensure that when you report the BOM as finished, the following occurs: - Component items from the BOM are reported as finished…

The correct answer is C. The Explosion option to Shortage. The "explosion" parameter defines how AX will consume the on hand inventory of the Shortage: Sub BOMs are only exploded if there is insufficient on hand inventory. If there is a partial quantity of the Sub BOM available, AX will only explode the component quantities of the Sub…

supply chain operations

Question

You plan to report a bill of materials (BOM) as finished. You need to ensure that when you report the BOM as finished, the following occurs:

  • Component items from the BOM are reported as finished.
  • Component items from the sub-BOMs that are currently on-hand are

reported as finished. What should you set?

Options

  • AThe Reservation field to Automatic
  • BThe Explosion option to Always
  • CThe Explosion option to Shortage
  • DThe Reservation field to Explosion

How the community answered

(39 responses)
  • A
    5% (2)
  • B
    8% (3)
  • C
    74% (29)
  • D
    13% (5)

Explanation

The "explosion" parameter defines how AX will consume the on hand inventory of the * Shortage: Sub BOMs are only exploded if there is insufficient on hand inventory. If there is a partial quantity of the Sub BOM available, AX will only explode the component quantities of the Sub BOM, for the difference. * Never: The Sub BOM is never exploded if there is a component shortage * Always: The Sub BOM is always exploded, and any free on hand inventory of the Sub BOM is