You need to create a new version of a bill of materials (BOM). Which three options can be used to create a new version of the BOM? Each correct answer presents part of the solution.

The correct answer is B. Dates C. Line type D. Quantities. To create another version of the new BOM, click CTRL+N in the Versions grid to create a new Select the relevant item number, and enter dates in the From date and To date fields to control the validity period of the BOM version. Use the From qty. field to set a minimum item…

supply chain operations

Question

You need to create a new version of a bill of materials (BOM). Which three options can be used to create a new version of the BOM? Each correct answer presents part of the solution.

Options

  • AWarehouse
  • BDates
  • CLine type
  • DQuantities
  • ESite

How the community answered

(15 responses)
  • A
    20% (3)
  • B
    73% (11)
  • E
    7% (1)

Explanation

To create another version of the new BOM, click CTRL+N in the Versions grid to create a new Select the relevant item number, and enter dates in the From date and To date fields to control the validity period of the BOM version. Use the From qty. field to set a minimum item quantity for using the BOM version. Click Approve to approve the BOM version. Select the Active check box to make the BOM version active.

Topics

#BOM versions#dates#quantities#line type