During which phase of a waterfall delivery is the creation and delivery of a complete system configuration performed?

The correct answer is A. development. See the full explanation below for the reasoning.

Question

During which phase of a waterfall delivery is the creation and delivery of a complete system configuration performed?

Options

  • Adevelopment
  • Bdata migration
  • Canalysis
  • Ddesign

How the community answered

(30 responses)
  • A
    80% (24)