Which activity is a precondition for communication management?
The correct answer is B. identifying project stakeholders. See the full explanation below for the reasoning.
Question
Which activity is a precondition for communication management?
Options
- Adefining project roles
- Bidentifying project stakeholders
- Canalyzing risk
- Ddefining project scope
How the community answered
(55 responses)- A4% (2)
- B73% (40)
- C5% (3)
- D18% (10)