Question
You and your team completed a successful deployment and Go-live cutover. In the first week following the Go-live cutover, your customer reports issues related to system setup and configuration. The customer asks to add fields to a report and to assist users in completing the new work procedures. How do you manage these requests?
Options
- AMake an application consultant available for remote and/or on-site support during these two weeks.
- BConfirm that your team is able to help and resolve the issue. The customer needs to be informed that the
- CUpdate this new information in the project's risk register, and then immediately plan a Steering Committee
- DImplement the Customization Review optimization offering to make sure that the quality of the