You and your team completed a successful deployment and Go-live cutover. In the first week following the Go-live cutover, your customer reports issues related to system setup and configuration. The…

The correct answer is A. Make an application consultant available for remote and/or on-site support during these two weeks. See the full explanation below for the reasoning.

Question

You and your team completed a successful deployment and Go-live cutover. In the first week following the Go-live cutover, your customer reports issues related to system setup and configuration. The customer asks to add fields to a report and to assist users in completing the new work procedures. How do you manage these requests?

Options

  • AMake an application consultant available for remote and/or on-site support during these two weeks.
  • BConfirm that your team is able to help and resolve the issue. The customer needs to be informed that the
  • CUpdate this new information in the project's risk register, and then immediately plan a Steering Committee
  • DImplement the Customization Review optimization offering to make sure that the quality of the

How the community answered

(37 responses)
  • A
    78% (29)
  • B
    14% (5)
  • C
    5% (2)
  • D
    3% (1)