Microsoft
MB5-858 · Question #42
The project manager finalized the schedule for the project after the kick-off meeting with the customer. In the weeks following, the team members requested several changes to some planned…
The correct answer is B. Yes, the schedule is a living document. See the full explanation below for the reasoning.
Question
The project manager finalized the schedule for the project after the kick-off meeting with the customer. In the weeks following, the team members requested several changes to some planned activities. Should the project manager adjust the schedule?
Options
- ANo, after the schedule is finalized it cannot be altered without formal approval of the steering committee.
- BYes, the schedule is a living document
- CYes, the schedule can still change after being finalized but only during the Tollgate Review meeting.
- DNo, only the Business Decision Maker can still change the agreed upon scheduled dates.
How the community answered
(54 responses)- A6% (3)
- B78% (42)
- C4% (2)
- D13% (7)
Community Discussion
No community discussion yet for this question.