You explain to your customer that you will use a formal project status report. How should you describe this document to your customer? Choose the 2 that apply.
The correct answer is B. The status report is a document prepared by the consulting project manager on a weekly basis. C. The status report is a document that is first reviewed with the project team through an internal weekly. See the full explanation below for the reasoning.
Question
You explain to your customer that you will use a formal project status report. How should you describe this document to your customer? Choose the 2 that apply.
Options
- AThe status report is a document prepared by the customer project manager on a weekly basis.
- BThe status report is a document prepared by the consulting project manager on a weekly basis.
- CThe status report is a document that is first reviewed with the project team through an internal weekly
- DThe status report is a document that is first reviewed with the key user team through an internal weekly
How the community answered
(47 responses)- A19% (9)
- B70% (33)
- D11% (5)
Community Discussion