MB5-858 · Question #3
You are determining the contract type for a new engagement. Based on the available diagnostic information, you come to the following conclusions: - There is uncertainty about a majority of the…
The correct answer is B. Time and Material. See the full explanation below for the reasoning.
Question
You are determining the contract type for a new engagement. Based on the available diagnostic information, you come to the following conclusions:
- There is uncertainty about a majority of the requirements
- There is a significant gap between a large set of requirements and
your Microsoft Dynamics solution
- Your project team is not familiar with the customers's industry
- Your customer is not familiar with implementation projects and
business software. Which contract type should you recommend?
Options
- AFixed price
- BTime and Material
- CFixed Price for Analysis and Design, Estimate for Development and Deployment
- DEstimate for Analysis and Design, Fixed Price for Development and Deployment
How the community answered
(36 responses)- A3% (1)
- B81% (29)
- C6% (2)
- D11% (4)