Which two activities are objectives of a project closure? (Each answer presents part of the solution. Choose two.)

The correct answer is B. Obtain formal sign-off on all deliverables. C. Ensure that the client is satisfied with the project outcome. See the full explanation below for the reasoning.

Question

Which two activities are objectives of a project closure? (Each answer presents part of the solution. Choose two.)

Options

  • ADocument the changes in scope.
  • BObtain formal sign-off on all deliverables.
  • CEnsure that the client is satisfied with the project outcome.
  • DCommunicate budget status.

How the community answered

(25 responses)
  • A
    8% (2)
  • B
    80% (20)
  • D
    12% (3)