MB5-858 · Question #116

You are a project manager and you are using the waterfall delivery for a project. Which two items must be completed within the development phase? (Each correct answer presents part of the solution…

The correct answer is A. project design B. custom coding. See the full explanation below for the reasoning.

Question

You are a project manager and you are using the waterfall delivery for a project. Which two items must be completed within the development phase? (Each correct answer presents part of the solution. Choose two.)

Options

  • Aproject design
  • Bcustom coding
  • Canalysis phase
  • Dproduction specifications
  • Edesign phase

How the community answered

(39 responses)
  • A
    85% (33)
  • C
    8% (3)
  • D
    5% (2)
  • E
    3% (1)

Community Discussion

No community discussion yet for this question.