You are a project manager working with a client who has specific feature needs, moderate to complex customizations, and minimal business process mapping completed. You need to recommend a project…

The correct answer is A. agile. Agile Implementation: Uses an iterative, incremental process for developing Microsoft Dynamics Solutions. This project gives customer greater control over the final solution because customers can quickly change the direction of the solution from one sprint cycle to…

Plan Microsoft Dynamics implementation projects

Question

You are a project manager working with a client who has specific feature needs, moderate to complex customizations, and minimal business process mapping completed. You need to recommend a project type for the client. Which project type should you recommend?

Options

  • Aagile
  • Benterprise
  • Cstandard
  • Drapid

How the community answered

(57 responses)
  • A
    75% (43)
  • B
    14% (8)
  • C
    4% (2)
  • D
    7% (4)

Explanation

Agile Implementation: Uses an iterative, incremental process for developing Microsoft Dynamics Solutions. This project gives customer greater control over the final solution because customers can quickly change the direction of the solution from one sprint cycle to next.Typically used at a single site requiring specific features and moderate to complex agile-implementation.aspx

Topics

#project type selection#agile#customizations#business process mapping