MB-920 · Question #111
A company is evaluating the capabilities of Dynamics 365 Supply Chain Management for its new research and development projects. The company plans to use only core functionality natively built into…
The correct answer is C. master planning. Master planning allows companies to determine and balance the future need for raw materials and capacity to meet company goals. Master planning assesses which raw materials and capacities are currently available, and which raw materials and capacities are required to complete…
Question
Options
- AInternet of Things
- BDynamics 365 Project Operations
- Cmaster planning
- Dgeneral ledger
- EPower Apps
How the community answered
(39 responses)- A3% (1)
- C92% (36)
- D5% (2)
Explanation
Master planning allows companies to determine and balance the future need for raw materials and capacity to meet company goals. Master planning assesses which raw materials and capacities are currently available, and which raw materials and capacities are required to complete production. For example, what must be manufactured, purchased, transferred, or set aside as safety stock before you can complete production. https://learn.microsoft.com/en-us/training/paths/master-planning-supply-chain-management/