Microsoft
MB-500 · Question #159
Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution. Determine whether the solution meets the stated goals…
The correct answer is B. No. Just extend CalendarName. Note: There are several properties that can be customized on existing extended data types (EDTs) through extension: You can only set the new String size to a value equal to or larger than the base EDT value. - Country region codes…
Design and develop AOT elements
Question
Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution. Determine whether the solution meets the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution. After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen. A company uses Dynamics 365 Finance. You are customizing elements for the extended data types (EDTs) shown in the following table. You have a table named WorkCalendar. The table has a column named BasicCalendarID that uses the BasicCalendarID EDT. You need to increase the length of the column by using an extension. Solution: Create an extension for CalendarName. Does the solution meet the goal?
Exhibit
Options
- AYes
- BNo
How the community answered
(32 responses)- A13% (4)
- B88% (28)
Explanation
Just extend CalendarName. Note: There are several properties that can be customized on existing extended data types (EDTs) through extension: You can only set the new String size to a value equal to or larger than the base EDT value. - Country region codes https://docs.microsoft.com/en-us/dynamics365/fin-ops-core/dev-itpro/extensibility/modify-edt
Topics
#Extended Data Types#EDT customization#AOT elements#D365 Finance
Community Discussion