You are configuring the production floor execution interface in Dynamics 365 Supply Chain Management. The current configuration of the production floor execution interface hinders efficient…
The correct answer is D. Disable Report quantity at clock-out and Lock employee. Select specific tabs to display in the production floor execution interface. The Tab selection FastTab Use the settings on the Tab selection FastTab to select which tabs the production floor execution interface should show when the current configuration is active. You can…
Question
You are configuring the production floor execution interface in Dynamics 365 Supply Chain Management. The current configuration of the production floor execution interface hinders efficient production floor operations and impedes worker productivity. You need to optimize the production floor execution interface configuration. What should you do?
Options
- ATurn off Generate license plate and Print label.
- BActivate Allow locking the touchscreen and then specify a Screen lock duration.
- CEnable Use the actual time of registration and Single worker.
- DDisable Report quantity at clock-out and Lock employee.
How the community answered
(43 responses)- A2% (1)
- B12% (5)
- C5% (2)
- D81% (35)
Explanation
- Select specific tabs to display in the production floor execution interface. The Tab selection FastTab Use the settings on the Tab selection FastTab to select which tabs the production floor execution interface should show when the current configuration is active. You can design as many tabs as you need, and then add and arrange them as you require by using the buttons on the FastTab * Disable Report quantity at clock-out and Lock employee. Report quantity at clock-out - Set this option to Yes to prompt workers to report feedback about jobs that are in progress when they clock out. When this option is set to No, workers won't be Lock employee - When this option is set to No, workers will be signed out immediately after they make a registration (such as a new job). The interface will then return to the sign-in page. When this option is set to Yes, workers will stay signed in to the production floor execution interface. However, a worker can manually sign out so that another worker can sign in while the production floor execution interface continues to run under the same system user account. * Activate Allow locking the touchscreen and then specify a Screen lock duration. * Deactivate Use the actual time of registration and Single worker. * Enable Use the actual time of registration and Single worker. * Set Report quantity at clock-out to Yes and Lock employee to Yes. * Turn off Generate license plate and Print label. https://learn.microsoft.com/en-us/dynamics365/supply-chain/production-control/production-floor- execution-configure Exam Questions, Study Guides, Practice Tests. Lead the way to help you pass any IT Certification exams, 100% Pass Guaranteed or Full Refund. Especially Cisco, Microsoft, CompTIA, Citrix, EMC, HP, Oracle, VMware, Juniper, Check Point, LPI, Nortel, EXIN and so on. Our Slogan: First Test, First Pass. Help you to pass any IT Certification exams at the first try. You can reach us at any of the email addresses listed below. Any problems about IT certification or our products, you could rely upon us, we will give you satisfactory answers in 24 hours.