A company plans to implement Dynamics 365 Supply Chain Management shipping manifests. The company wants to use a multiple-level manifest process. You need to ensure that the system is configured for…
The correct answer is A. All container groups are manifested before the shipment is manifested. If using a multiple level manifest procedure, it is a requirement that: - All containers must be manifested before container group is manifested. - All container groups must be manifested before shipment is manifested.
Implement warehouse management and transportation management
Question
A company plans to implement Dynamics 365 Supply Chain Management shipping manifests. The company wants to use a multiple-level manifest process. You need to ensure that the system is configured for multiple-level manifest processing. What should you validate?
Options
- AAll container groups are manifested before the shipment is manifested
- BAll containers are of the status open before the group is manifested
- CThe allow split picks configuration is enabled
- DAll container types are set up with all four attributes
How the community answered
(37 responses)- A78% (29)
- B5% (2)
- C14% (5)
- D3% (1)
Explanation
If using a multiple level manifest procedure, it is a requirement that: - All containers must be manifested before container group is manifested. - All container groups must be manifested before shipment is manifested.