You are a production manager at a company which produces large batches of coffee and creamers. After a quality inspection, batch 120008 of your cold brew coffee (item number CB-0001) was found to be…
The correct answer is B. Add 20 grams of sugar to the production formula D. Manually reserve batch 120008 after estimating the batch order E. Add a route operation for 0.5 run time hours of stirring. https://technologyblog.rsmus.com/microsoft-dynamics/dynamics-365-for-finance-and- operations/rework-batch-orders-in-microsoft-dynamics-365-for-finance-and- operationscmpidblogtmc-ms-dynamics-1219d01/
Manage manufacturing processes
Question
You are a production manager at a company which produces large batches of coffee and creamers. After a quality inspection, batch 120008 of your cold brew coffee (item number CB-0001) was found to be too acidic and must be reworked. You need to add 20 grams of sugar and stir the product for an additional 0.5 hours. What three actions are required on the rework order?Each correct answer presents part of the solution. NOTE: Each correct selection is worth one point.
Options
- ADelete all items from the production formula except for 20 grams of sugar
- BAdd 20 grams of sugar to the production formula
- CDelete all route operations except for a half an hour stirring operation
- DManually reserve batch 120008 after estimating the batch order
- EAdd a route operation for 0.5 run time hours of stirring
How the community answered
(25 responses)- A8% (2)
- B72% (18)
- C20% (5)
Explanation
https://technologyblog.rsmus.com/microsoft-dynamics/dynamics-365-for-finance-and- operations/rework-batch-orders-in-microsoft-dynamics-365-for-finance-and- operationscmpidblogtmc-ms-dynamics-1219d01/
Topics
#rework orders#batch orders#production formula#route operations