MB-320 · Question #66
A company uses Dynamics 365 Supply Chain Management for Process manufacturing. You are reviewing the planned production orders for the next two weeks. There are several production orders for the…
The correct answer is A. Rerun master planning. Select the static plan with a coverage time fence of two weeks. See the full explanation below for the reasoning.
Question
A company uses Dynamics 365 Supply Chain Management for Process manufacturing. You are reviewing the planned production orders for the next two weeks. There are several production orders for the same product. One order is scheduled to run the week after another order. You need to optimize the planned production orders. What should you do?
Options
- ARerun master planning. Select the static plan with a coverage time fence of two weeks.
- BFirm the orders
- CIn Planned orders, combine the production orders
- DRerun master planning. Select the dynamic plan with a coverage time fence of two weeks
How the community answered
(56 responses)- A73% (41)
- B7% (4)
- C16% (9)
- D4% (2)