The correct answer is C. From the schedule board, click Actions and select Optimize Schedule.. See the full explanation below for the reasoning.
Question
You restore Resource Schedule Optimization. You need to optimize individual resource schedules. What should you do?
Options
- AIn Field Service Administration, locate a Resource record and select Optimize Schedule.
- BFrom the schedule board, right-click a Resource record and select Optimize Schedule.
- CFrom the schedule board, click Actions and select Optimize Schedule.
- DIn Resource Schedule Optimization, locate a User record and select Optimize Schedule.