You are implementing Dynamics 365 Field Service. Your customer needs to understand how they can schedule the closest possible resource to a work order. The requirement further specifies it could be…

The correct answer is C. Update the filter on the Scheduler resource tool tips view. See the full explanation below for the reasoning.

Question

You are implementing Dynamics 365 Field Service. Your customer needs to understand how they can schedule the closest possible resource to a work order. The requirement further specifies it could be start of day from the company's site or during the middle of the day from an existing work order. You need to provide them with the settings they need to properly configure so the closest resource is found when using the schedule assistant. What should you suggest to the customer?

Options

  • AUpdate the Starting Location to Organization Unit on the Bookable Resource.
  • BUpdate the Resources Synchronization Timeout (in sec) within the Scheduling Parameters.
  • CUpdate the filter on the Scheduler resource tool tips view.
  • DUpdate the Load Default Filters on the Schedule Board.

How the community answered

(42 responses)
  • A
    7% (3)
  • B
    5% (2)
  • C
    71% (30)
  • D
    17% (7)