Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet stated goals. Some question sets might…

The correct answer is B. No. Set resource hourly rate is missing. Set resource work hours is missing. And holiday schedule should be business closures.

Perform configuration

Question

Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution. After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen. You are a Dynamics 365 for Field Service system administrator. You are configuring a new instance of Dynamics 365 for Field Service. The organization needs to accurately capture the cost of work order bookings. Solution: You implement the following configuration changes: 1) Create Resource Pay Types for regular, holiday, overtime, travel, and breaks. 2) Assign an Hourly Markup percentage to each Resource Pay Type. 3) Assign Resource Pay Types to the applicable Pay Type. 4) Create the Holiday Schedule. Does this meet the goal?

Options

  • AYes
  • BNo

How the community answered

(29 responses)
  • A
    21% (6)
  • B
    79% (23)

Explanation

Set resource hourly rate is missing. Set resource work hours is missing. And holiday schedule should be business closures.