MB-240 · Question #164
Your company recently implemented Microsoft Dynamics 365 Field Service. You helped set up and configure the required components to ensure that a work order can be created and completed successfully…
The correct answer is A. Estimated Duration in Service Task. See the full explanation below for the reasoning.
Question
Your company recently implemented Microsoft Dynamics 365 Field Service. You helped set up and configure the required components to ensure that a work order can be created and completed successfully. One of the dispatchers reports to their manager that the duration in the work order is missing. You need to ensure the duration is rolled-up to the work order duration. Which component must you configure?
Options
- AEstimated Duration in Service Task
- BHourly Rate of the Resources
- CPricing in Product / Service
- DStart Date and End Date in Service Task
How the community answered
(27 responses)- A78% (21)
- B11% (3)
- C4% (1)
- D7% (2)