LEAD-AUDITOR · Question #17

What is we do in ACT - From PDCA cycle

The correct answer is B. Take actions to continually improve process performance. In the Act phase of the PDCA cycle, the process is reviewed and evaluated based on the results from the Check phase. The actions taken in this phase aim to continually improve the process performance by addressing the root causes of problems, implementing corrective and preventiv

ISMS Continual Improvement

Question

What is we do in ACT - From PDCA cycle

Options

  • ATake actions to continually monitor process performance
  • BTake actions to continually improve process performance
  • CTake actions to continually monitor process performance
  • DTake actions to continually improve people performance

How the community answered

(21 responses)
  • A
    14% (3)
  • B
    76% (16)
  • C
    5% (1)
  • D
    5% (1)

Explanation

In the Act phase of the PDCA cycle, the process is reviewed and evaluated based on the results from the Check phase. The actions taken in this phase aim to continually improve the process performance by addressing the root causes of problems, implementing corrective and preventive actions, and updating the process documentation.

Topics

#PDCA cycle#Act phase#continual improvement#process performance

Community Discussion

No community discussion yet for this question.