LEAD-AUDITOR · Question #16
Implement plan on a test basis - this comes under which section of PDCA
The correct answer is B. Do. The PDCA cycle is a four-step method for managing and improving processes. The steps are Plan, Do, Check, and Act. In the Plan phase, the objectives and scope of the process are defined, and the resources and activities are planned. In the Do phase, the process is implemented on
Question
Implement plan on a test basis - this comes under which section of PDCA
Options
- APlan
- BDo
- CAct
- DCheck
How the community answered
(51 responses)- A8% (4)
- B73% (37)
- C16% (8)
- D4% (2)
Explanation
The PDCA cycle is a four-step method for managing and improving processes. The steps are Plan, Do, Check, and Act. In the Plan phase, the objectives and scope of the process are defined, and the resources and activities are planned. In the Do phase, the process is implemented on a test basis, and the results are recorded and analyzed.
Topics
Community Discussion
No community discussion yet for this question.