What are two prerequisites of capacity planning in a network design? (Choose two.)
The correct answer is A. predicting traffic projections for future growth C. understanding current application behavior. Capacity planning requires knowing where you are now (C) and where you're going (A) - you need to understand current application behavior to establish a baseline, and you need traffic projections to anticipate future demand and size the network accordingly. Without both, you're…
Question
What are two prerequisites of capacity planning in a network design? (Choose two.)
Options
- Apredicting traffic projections for future growth
- Bunderstanding historical application behavior
- Cunderstanding current application behavior
- Dunderstanding historical growth
How the community answered
(48 responses)- A90% (43)
- B4% (2)
- D6% (3)
Explanation
Capacity planning requires knowing where you are now (C) and where you're going (A) - you need to understand current application behavior to establish a baseline, and you need traffic projections to anticipate future demand and size the network accordingly. Without both, you're either guessing at the starting point or flying blind about growth.
Why B and D are wrong: Historical data is useful context but not a prerequisite - you can plan capacity without knowing past behavior or past growth rates, as long as you have current state and future projections. History informs forecasts but doesn't replace them; the actual planning inputs are the current baseline and the forward-looking projection.
Memory tip: Think of capacity planning like planning a road trip - you need to know your current location (C: current behavior) and your destination (A: future projections). Where you've been (history) is nice to know but won't stall the trip if you don't have it.