Which capacity management sub-process focuses on the management, control and prediction of the end-to-end performance?
The correct answer is C. Service capacity management. https://advisera.com/20000academy/knowledgebase/three-faces-capacity-management/
Selected processes
Question
Which capacity management sub-process focuses on the management, control and prediction of the end-to-end performance?
Options
- ABusiness capacity management
- BSupplier capacity management
- CService capacity management
- DComponent capacity management
How the community answered
(37 responses)- A3% (1)
- B14% (5)
- C76% (28)
- D8% (3)
Explanation
https://advisera.com/20000academy/knowledgebase/three-faces-capacity-management/
Topics
#capacity management#service capacity management#end-to-end performance#sub-process