In which of the following should details of a workaround be documented?
The correct answer is B. The problem record. See the full explanation below for the reasoning.
Question
In which of the following should details of a workaround be documented?
Options
- AThe service level agreement (SLA)
- BThe problem record
- CThe availability management information system
- DThe IT service plan
How the community answered
(35 responses)- A3% (1)
- B80% (28)
- C6% (2)
- D11% (4)