Which process works with change management to ensure only authorized components are used?
The correct answer is C. Service asset and configuration management. See the full explanation below for the reasoning.
Question
Which process works with change management to ensure only authorized components are used?
Options
- AKnowledge management
- BService portfolio management
- CService asset and configuration management
- DFinancial management for IT services
How the community answered
(26 responses)- A4% (1)
- B4% (1)
- C85% (22)
- D8% (2)