nerdexam
PeopleCert

ITIL-F · Question #433

Which of the following is NOT an aim of the Change Management process?

The correct answer is C. All budgets and expenditures are accounted for. See the full explanation below for the reasoning.

Question

Which of the following is NOT an aim of the Change Management process?

Options

  • AOverall business risk is optimized
  • BStandardized methods and procedures are used for efficient and prompt handling of all Changes
  • CAll budgets and expenditures are accounted for
  • DAll changes to Service Assets and Configuration Items (CIs) are recorded in the Configuration

How the community answered

(29 responses)
  • A
    10% (3)
  • B
    3% (1)
  • C
    83% (24)
  • D
    3% (1)

Community Discussion

No community discussion yet for this question.

Full ITIL-F Practice