ITIL-F · Question #382
Order the following continual service improvement (CSI) implementation steps into the correct sequence in alignment with the plan, Do, Check, Act (PDCA) model. (1) Allocate roles and…
The correct answer is A. 3-1-2-4. See the full explanation below for the reasoning.
Question
Order the following continual service improvement (CSI) implementation steps into the correct sequence in alignment with the plan, Do, Check, Act (PDCA) model. (1) Allocate roles and responsibilities to work on CSI initiatives. (2) Measure and review that the CSI plan is executed and its objectives are being achieved. (3) Identify the scope, objectives and requirements for CSI. (4) Decision on implementation of further enhancement.
Options
- A3-1-2-4
- B3-4-2-1
- C1-3-2-4
- D2-3-4-1
How the community answered
(40 responses)- A78% (31)
- B3% (1)
- C8% (3)
- D13% (5)
Community Discussion
No community discussion yet for this question.