ITIL-F · Question #248

Which of the following items would commonly be on the agenda for a change advisory board (CAB)? 1. Details of failed changes 2. Updates to the change schedule 3. Reviews of completed changes

The correct answer is A. All of the above. See the full explanation below for the reasoning.

Question

Which of the following items would commonly be on the agenda for a change advisory board (CAB)? 1. Details of failed changes 2. Updates to the change schedule 3. Reviews of completed changes

Options

  • AAll of the above
  • B1 and 2only
  • C2 and 3 only
  • D1 and 3 only

How the community answered

(26 responses)
  • A
    77% (20)
  • B
    4% (1)
  • C
    8% (2)
  • D
    12% (3)