ISTQB-CTFL · Question #93
A company runs a pilot project for evaluation of a test automation tool. Which of the following is NOT a valid object of this pilot project?
The correct answer is C. Train all testers on using the tool. A pilot project is a small-scale experiment or trial that is conducted to evaluate the feasibility, effectiveness, and suitability of a test automation tool before implementing it on a larger scale. The objectives of a pilot project may vary depending on the context and scope…
Question
A company runs a pilot project for evaluation of a test automation tool. Which of the following is NOT a valid object of this pilot project?
Options
- AGet familiar with the functionality and options of the tool
- BCheck haw the tool fits to the existing test processes
- CTrain all testers on using the tool
- DDecide upon standards for tool implementation
How the community answered
(26 responses)- A4% (1)
- B4% (1)
- C81% (21)
- D12% (3)
Explanation
A pilot project is a small-scale experiment or trial that is conducted to evaluate the feasibility, effectiveness, and suitability of a test automation tool before implementing it on a larger scale. The objectives of a pilot project may vary depending on the context and scope of the test automation initiative, but some common ones are: To get familiar with the functionality and options of the tool To check how the tool fits to the existing test processes and environment To assess the benefits and challenges of using the tool To decide upon standards and guidelines for tool implementation and usage To estimate the costs and resources required for tool deployment and maintenance