ISTQB-CTFL · Question #70

A new testing tool has been selected for an organisation and a pilot project has successfully completed. The next step is to deploy the tool within the organization. What is a key success factor in…

The correct answer is A. Estimate a cost-benefit ratio based on a firm business case. Estimating a cost-benefit ratio through a firm business case is the key success factor at the deployment stage because the organisation needs a quantified justification to secure the resources, budget, and stakeholder buy-in required to roll the tool out beyond the pilot…

Tool Support for Testing

Question

A new testing tool has been selected for an organisation and a pilot project has successfully completed. The next step is to deploy the tool within the organization. What is a key success factor in tool deployment?

Options

  • AEstimate a cost-benefit ratio based on a firm business case
  • BDetermine whether benefits will be achieved at reasonable cost
  • CProvide support for the test team using the tool
  • DAssessment of organisational maturity, strengths and weaknesses

How the community answered

(33 responses)
  • A
    88% (29)
  • B
    6% (2)
  • C
    3% (1)
  • D
    3% (1)

Explanation

Estimating a cost-benefit ratio through a firm business case is the key success factor at the deployment stage because the organisation needs a quantified justification to secure the resources, budget, and stakeholder buy-in required to roll the tool out beyond the pilot. Without this formal foundation, deployment efforts lack organisational legitimacy and are likely to stall.

Why the distractors are wrong:

  • B - Determining whether benefits can be achieved at reasonable cost is an evaluation activity that should occur before the pilot, not after it has already succeeded; that question has been answered.
  • D - Assessing organisational maturity, strengths, and weaknesses is part of tool selection, not deployment; it belongs even earlier in the process.
  • C - Providing support for the test team is an ongoing operational concern during use, not a key success factor for the deployment phase itself.

Memory tip: Think of deployment as needing to "sell" the tool internally - and every internal sale requires a business case. The sequence is: assess organisation → select tool → pilot → build the business case → deploy. If you remember that order, A stands out as the only answer that belongs at the deployment stage.

Topics

#tool deployment#cost-benefit analysis#tool introduction#test tools