Which two of the following phrases would apply to "plan" in relation to the Plan-Do-Check-Act cycle for a business process?
The correct answer is D. Setting objectives E. Training staff. The Plan-Do-Check-Act (PDCA) cycle is a four-step method for implementing and improving processes, products, or services. The "plan" phase involves establishing the objectives and processes necessary to deliver the desired results. This may include setting SMART goals…
Question
Which two of the following phrases would apply to "plan" in relation to the Plan-Do-Check-Act cycle for a business process?
Options
- ARetaining documentation
- BRetaining documentation
- COrganising changes
- DSetting objectives
- ETraining staff
- FProviding ICT assets
How the community answered
(36 responses)- A3% (1)
- D92% (33)
- F6% (2)
Explanation
The Plan-Do-Check-Act (PDCA) cycle is a four-step method for implementing and improving processes, products, or services. The "plan" phase involves establishing the objectives and processes necessary to deliver the desired results. This may include setting SMART goals, identifying resources, defining roles and responsibilities, conducting risk assessments, and developing plans for training, communication, and monitoring.