Which one of the following methods for test estimation rely on information captured from previous projects?
The correct answer is C. Metrics-based. See the full explanation below for the reasoning.
Question
Which one of the following methods for test estimation rely on information captured from previous projects?
Options
- ATest point-based
- BExpert-based
- CMetrics-based
- DDevelopment effort-based