Which one of the following methods for test estimation rely on information captured from previous projects?

The correct answer is C. Metrics-based. See the full explanation below for the reasoning.

Question

Which one of the following methods for test estimation rely on information captured from previous projects?

Options

  • ATest point-based
  • BExpert-based
  • CMetrics-based
  • DDevelopment effort-based

How the community answered

(56 responses)
  • A
    13% (7)
  • B
    5% (3)
  • C
    79% (44)
  • D
    4% (2)