nerdexam
BCS-ISEB

ISEB-SWT2 · Question #116

Which of the following is a project risk?

The correct answer is B. We may not be able to get a contractor to join the test team as planned. See the full explanation below for the reasoning.

Question

Which of the following is a project risk?

Options

  • AThere are non-standard implementations of some features
  • BWe may not be able to get a contractor to join the test team as planned
  • CThe response times of the software may not be fast enough
  • DThe contract has a legal loophole which has affected the company profit The contract has a legal

How the community answered

(70 responses)
  • A
    3% (2)
  • B
    84% (59)
  • C
    4% (3)
  • D
    9% (6)

Community Discussion

No community discussion yet for this question.

Full ISEB-SWT2 Practice