Which of the following is a project risk?
The correct answer is B. We may not be able to get a contractor to join the test team as planned. See the full explanation below for the reasoning.
Question
Which of the following is a project risk?
Options
- AThere are non-standard implementations of some features
- BWe may not be able to get a contractor to join the test team as planned
- CThe response times of the software may not be fast enough
- DThe contract has a legal loophole which has affected the company profit The contract has a legal
How the community answered
(70 responses)- A3% (2)
- B84% (59)
- C4% (3)
- D9% (6)