ISEB-SWT2 Question #116: Real Exam Question with Answer & Explanation

The correct answer is B. We may not be able to get a contractor to join the test team as planned. See the full explanation below for the reasoning.

Question

Which of the following is a project risk?

Options

  • AThere are non-standard implementations of some features
  • BWe may not be able to get a contractor to join the test team as planned
  • CThe response times of the software may not be fast enough
  • DThe contract has a legal loophole which has affected the company profit The contract has a legal