Which of the following is a MAJOR activity of test control?

The correct answer is C. Making decisions based on information from test monitoring. See the full explanation below for the reasoning.

Question

Which of the following is a MAJOR activity of test control?

Options

  • AScheduling test analysis and design
  • BImplementing the test policy or strategy
  • CMaking decisions based on information from test monitoring
  • DDetermining the scope and risks

How the community answered

(30 responses)
  • A
    3% (1)
  • B
    13% (4)
  • C
    77% (23)
  • D
    7% (2)