The performing organization is trying to decide whether to split the contracts department and assign procurement responsibilities to departments directly responsible for the projects. A procurement…
The correct answer is D. Access to others with similar expertise. You've hit your session limit · resets 5:20pm (America/New_York)
Organizational Aspects of Project Management
Question
The performing organization is trying to decide whether to split the contracts department and assign procurement responsibilities to departments directly responsible for the projects. A procurement professional might not want this split to occur because they would lose ___________ in a decentralized contracting environment.
Options
- AStandardized company project management practices
- BLoyalty to the project
- CExperience
- DAccess to others with similar expertise
How the community answered
(28 responses)- A4% (1)
- B4% (1)
- C11% (3)
- D82% (23)
Explanation
You've hit your session limit · resets 5:20pm (America/New_York)
Topics
#centralized contracting#decentralized contracting#procurement organization