Organizational Aspects of Project Management
Question
ISEB ISEB-PM1 Exam The project manager has, as a prime responsibility, to assure proper integration of activities. In which organizational form does the project manager probably have the easiest time in integrating work?
Options
- AMatrix
- BPure project
- CCoordinator
- DClassical
- EExpediter
How the community answered
(28 responses)- A4% (1)
- B82% (23)
- C11% (3)
- D4% (1)
Explanation
You've hit your weekly limit · resets 5am (America/New_York)
Topics
#organizational structure#projectized organization#integration management#project authority