In an organization with a projectized organizational structure, who controls the project budget?
The correct answer is B. Project manager. In a projectized organizational structure, the project manager has full authority over the project, including complete control of the budget - making B correct. This structure exists at the opposite end of the spectrum from functional organizations, where authority rests with…
Question
In an organization with a projectized organizational structure, who controls the project budget?
Options
- AFunctional manager
- BProject manager
- CProgram manager
- DProject management office
How the community answered
(45 responses)- A4% (2)
- B82% (37)
- C11% (5)
- D2% (1)
Explanation
In a projectized organizational structure, the project manager has full authority over the project, including complete control of the budget - making B correct. This structure exists at the opposite end of the spectrum from functional organizations, where authority rests with department heads.
Why the distractors are wrong:
- A (Functional manager): Functional managers control budgets in functional organizational structures, where projects are secondary to departmental work. In a projectized structure, they have little to no authority.
- C (Program manager): A program manager oversees a group of related projects but does not directly control any individual project's budget - that authority stays with the project manager.
- D (PMO): The PMO provides governance, standards, and support, but does not own or control individual project budgets.
Memory tip: Think of the word "projectized" as meaning the project is king - so the project manager rules everything on that project, including the budget, schedule, and resources.