ISEB-PM1 · Question #273
A project manager is responsible for managing which of the following at the project level?
The correct answer is C. Constraints. Constraints (C) are managed at the project level because they are specific to each project - things like budget, schedule, scope, quality, resources, and risk that a PM must balance and control throughout the project lifecycle. Managing constraints is the core operational…
Question
A project manager is responsible for managing which of the following at the project level?
Options
- AMethodology
- BStandards
- CConstraints
- DInterdependencies
How the community answered
(53 responses)- A4% (2)
- B6% (3)
- C77% (41)
- D13% (7)
Explanation
Constraints (C) are managed at the project level because they are specific to each project - things like budget, schedule, scope, quality, resources, and risk that a PM must balance and control throughout the project lifecycle. Managing constraints is the core operational responsibility of a project manager.
Why the distractors are wrong:
- A. Methodology - Methodologies (Agile, Waterfall, PRINCE2, etc.) are typically selected or mandated at the organizational or program level, not defined by individual PMs per project.
- B. Standards - Standards are set by the organization, industry bodies, or governance frameworks (PMI, ISO, etc.), sitting above the project level.
- D. Interdependencies - While a PM is aware of interdependencies, managing them across projects is a program or portfolio management responsibility; a PM manages dependencies within the project.
Memory tip: Think of the "Iron Triangle" - cost, time, scope - these are all constraints. A PM juggles these every day at the project level. If it applies to your project specifically, it's likely a constraint.