Which process includes business, service and component sub-processes?
The correct answer is A. Capacity management. See the full explanation below for the reasoning.
Question
Which process includes business, service and component sub-processes?
Options
- ACapacity management
- BIncident management
- CService level management
- DFinancial management
How the community answered
(64 responses)- A75% (48)
- B3% (2)
- C6% (4)
- D16% (10)
Community Discussion