Which of the following does the Availability Management process include? 1. Ensuring services are able to meet availability targets 2. Monitoring and reporting actual availability 3. Improvement…

The correct answer is C. All of the other alternatives apply. See the full explanation below for the reasoning.

Question

Which of the following does the Availability Management process include? 1. Ensuring services are able to meet availability targets 2. Monitoring and reporting actual availability 3. Improvement activities, to ensure that services continue to meet or exceed their availability goals

Options

  • A1 and 2 only
  • B1 and 3 only
  • CAll of the other alternatives apply.
  • D1 only

How the community answered

(55 responses)
  • A
    13% (7)
  • B
    4% (2)
  • C
    78% (43)
  • D
    5% (3)