The correct answer is C. Emergency Change Advisory Board (ECAB). See the full explanation below for the reasoning.
Question
The group that reviews Changes that must be installed faster than the normal Change process is called the:
Options
- ATechnical Management (TM)
- BUrgent Change Authority (UCA)
- CEmergency Change Advisory Board (ECAB)
- DUrgent Change Board (UCB)